banner ad
Experts Logo

articles

Acceleration Claims on Engineering and Construction Projects

By: Long International, Inc. - Richard Long P.E.
Tel: (303) 972-2443
Email:Long International, Inc.


View Profile on Experts.com.


1. INTRODUCTION

Time is money especially on engineering and construction projects. Because delays in the completion of the project usually result in increased owner, engineer, and contractor costs, the overall time of performance is vital to the financial success of the project. The importance of time is evidenced by the significant role played by CPM schedules, completion dates, and milestones in the bidding and awarding of engineering and construction contracts. The desire to minimize costs and the time of performance often causes the occurrence of acceleration.

This article discusses the following topics:1

  • Types of Acceleration;
  • Key Elements of Acceleration Required by the Courts;
  • Acceleration Claims Outside of the United States;
  • Notice Requirements;
  • The Relevance of the Date When the Time Extension Is Given;
  • Contract Provisions Associated with Acceleration;
  • The Effect of a "No Damage For Delay" Clause on Acceleration;
  • Identifying Acceleration Using the Project Schedules;
  • Documenting Acceleration Evidence; and
  • Acceleration Damages.

2. TYPES OF ACCELERATION

There are three types of acceleration: directed acceleration, constructive acceleration, and voluntary acceleration.

Directed acceleration occurs when the owner or construction manager issues a specific order to its construction contractor under the contract provisions to 1) complete the project earlier than the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to complete the base contract work plus additional or changed work within the original contract time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to make-up for contractor-caused delays that threaten the on-time completion of the project. These measures can result in costs being incurred that would not otherwise have been required.

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

long-international-logo.jpg

7/5/2022· Construction

Assessment Of Problems Associated With Poor Project Management Performance

By: Long International

The purpose of this paper is to provide an explanation of the methodology and resources that Long International uses to arrive at its opinions on allocation of the responsibility for various problems, and the impact of those opinions on the parties’ entitlement to damages or extensions of the time of performance allowed under a Contract.

long-international-logo.jpg

4/13/2012· Construction

Construction Disputes: Schedule and Delay Analysis Methodologies

By: Long International

The equitable allocation of responsibility for project delays is essential to the resolution of many construction disputes. Contractors frequently assert that they have been delayed for reasons beyond their control. Owners often remain unconvinced that the Contractor is legitimately entitled to a time extension or delay, acceleration and loss of productivity damages.

coleman-horowitt-logo.jpg

6/21/2018· Construction

Court Determines Sanitary District Can Use Its Own Employees for Construction Projects

By: Darryl Horowitt

The Public Contracts Code generally provides that contracts for certain dollar amounts, generally exceeding $15,000 to $25,000, must be sent out for bid and let to the lowest responsible bidder after appropriate notice is given. Public Contracts Code § 20803, which governs sanitary districts, contains such a requirement for any contract exceeding $15,000.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;